См. также: акт милосердия, акт об оказанных услугах, акт осмотра, акт предательства
the remaining 5% upon the expiration of the Defects Liability Period [i.e. 12 months from the issuance of the Substantial Completion Certificate] for the whole of the Main Contract provided the Architect has certified [the “Defects Rectification Certificate”] that all defects have been made good (“the Final Payment”).” (Schindler Lifts (Hong Kong) Ltd v Sui Chong Construction And Engineering Co Ltd)
Defects Rectification Certificate means a certificate issued by the Contract Administrator signifying the completion to his satisfaction of rectification of all defects notified by him to be rectified in such works section of the Main Contract which includes a Sub-Contract Works Section. (LawInsider)